|
|
|
|
Abu Dhabi’s construction industry can now
reduce its environmental impact thanks to
the opening of a new specialised processing
plant designed and built by Thiess Services
Middle East (TSME) to manage construction
and demolition debris.
TSME, a joint venture between Al Habtoor
Leighton Group and Australia’s Thiess
Services, designed the plant to meet the
requirements of its 15-year waste
management concession contract with the
Center of Waste Management Abu Dhabi.
The plant allows construction waste to be
processed and recycled for other uses such
as roadbase, general fill and aggregates for
construction and infrastructure projects.
At the opening ceremony on the 10th
of May, TSME’s General Manager, Tim
Harwood, said the plant was the largest and most
sophisticated of its type in the Middle East.
“Not only does this plant provide opportuni-
ties to re-use and manage construction waste
within Abu Dhabi, it also reduces demand
on natural resources and quarries in other
locations in the UAE,” he said.
Boasting the latest in safety features and
technology, the new plant is capable of
processing more than 7,000 tonnes of
material per day. The products generated from this plant meet all international quality standards and in many cases have
been shown to outperform natural quarried
products.
“Abu Dhabi is
taking its carbon
footprint reduction
strategy very seriously
with projects such as
this and we are pleased
to be part of such a
worthy initiative,” said
Tim. He congratulated
the Center of Waste
Management on their
vision to find a clean-
er, greener way to
manage construction
waste in the Emirate.
TSME is looking forward to contributing to
this vision by providing the market with the option to use high-quality recycled products.
|
|
|
Thiess Services Middle East has been award-
ed the GCC Sanitation & Waste Management
Contractor/Service of the Year Award at the
Facilities Management Middle East Awards
2010.
The award was presented at the annual Facilities Management Middle East Awards 2010
gala dinner on 19th May, and recognised TS-
ME’s work in waste collection and recycling
in Abu Dhabi.
In addition to receiving the award, Thiess
Services Middle East was also shortlisted for
five other awards.
Tim Harwood said that TSME was proud to
receive the award for its work in Abu Dhabi.
“This is great recognition for the hard
work of the TSME
team and indicates
there is a growing
need and demand
for a sustainable
approach to waste
management and
recycling in this region.”
|
|
The project team for the St. Regis Hotel on
Abu Dhabi’s Saadiyat Island has reached a key
milestone, having met its first structural completion date earlier than scheduled.
The project, which is a joint venture with HLG
and Murray & Roberts, began in August 2009
and is due for completion in August 2011.
The contract is for the 380 luxury hotel rooms,
259 residential apartments and 33 luxury resi-
dential villas. The project also features a retail
and entertainment component, a health and
racquet club, a health spa and 1,600 struc-
tured parking bays.
Senior Project Manager, Gus Heber, said initial works involved the construction of many
deep basement pits and water tanks below
the water table and several metres beneath
the hotel basement area, as well as a three-
level underground basement car park for the
Apartment Complex.
“Since August 2009, the extensive structural
works have now made their way out of the
ground which covers a substantial footprint of approximately 350,000 square metres,” he
said.
“During this period the raft slabs of the 33
surrounding villas have been dotting the
perimeter while a dedicated underground
service tunnel for the hotel’s service vehicles
and main incoming chilled water supply has
been making its way forward from the site entry and is about 70 per cent complete.
“Concrete placement on site is currently aver-
aging 4,000 cubic metres per week.”
Mr Heber said the first of
seven apartment buildings
reached structural comple-
tion on May 26 - three days
before the original con-
tract requirement date. The
structural works in total are
programmed to continue
until November 2010.
“The achievement of the
first structural completion date earlier than programmed was an important milestone for the
project,” he said.
“Currently the site workforce is 3,000 men
and this will increase to about 6,000 men later this year as the structural works complete
and the internal works and external cladding
will be in full swing.
“The hotel structure is 40 per cent complete
and structural works for the 33 villas surrounding the hotel and apartments are about
50 per cent complete, so we are pleased with
the way we are tracking at the moment.”
|
|
|
|
|
Home
|
Al Habtoor Group
| Habtoor Hotels |
Al Habtoor
Motors
|
|
Diamondlease
|
Emirates
International School
|
Al Habtoor Leighton Group
|
Copyright © 2010
Al Habtoor Group.
All Rights Reserved.
Articles, excerpts, and translations may not be reproduced in any form
without written permission of the Al Habtoor Group.
|
|
|