Habtoor Engineering Enterprises is
building a new grandstand and
refurbishing the existing facilities at
the Al Ain Club as part of the UAE’s
preparations for hosting the FIFA World
Youth Championships in 2003. Ben
Smalley reports.
The eyes of the football world will be on the UAE in a few months
time when the country hosts the FIFA
World Youth Championships - the
world’s biggest soccer tournament
after the World Cup.
The 24 best countries from around the globe will be
represented in the Under 20’s
competition, with matches taking place
at six stadiums across the UAE from
March 25 to April 16.
Preparation work is well underway ahead of the massive
event, including the construction of a
new grandstand and the complete
refurbishment of the existing facilities
at the Al Ain Club – one of the main
venues for the championship matches.
Al Habtoor Engineering Enterprises, the construction
arm of the Al Habtoor Group, won the
tender for the Dh 68 million project,
which will become an international
showcase for the quality and exceptional
standard of sports facilities in the UAE.
Project Manager Yehia Abdullah said: “The stadium
will take centre stage during the
championships. It is a flagship
development which reflects the UAE, and
we are pleased and honoured to be
involved with it.”
The main work involves the construction of a
3,500-seat grandstand, which will also
house the changing rooms for the teams,
media facilities and VIP areas for
dignitaries attending the matches.
“It consists of a basement, ground, first, second
and third floor,” Mr Abdullah
explained. “The basement is
essentially a service and storage area,
the ground floor is the central part of
the VIP foyer, and to the left and right
are the changing rooms, washrooms and
locker rooms for the teams.
“The first floor includes prayer rooms, as well as
washrooms and toilets for the VIPs. On
the second floor there is the VVIP
lounge, as well as conference and media
rooms, and the third floor consists of
suites where the VVIPs can relax, and
also the media broadcasting room,
control rooms for the scoreboards and
floodlights, and associated service
rooms.”
The contract awarded to Al Habtoor Engineering
Enterprises also includes providing a
new scoreboard, replacing the
floodlights, refurbishing existing
facilities and building a 1.5km boundary
wall around the site – all of which
have to be completed to exacting
standards.
“The stadium is being refurbished and a new
grandstand constructed for the FIFA
World Youth Championships, which means
they have to meet all the requirements
for stadiums as laid down by FIFA, the
governing body of world football,” Mr.
Abdullah explained. “For example,
there are certain specifications for the
scoreboard and the floodlights, and any
stadium has to meet those requirements
in order to be approved by FIFA.”
He added: “Basically we are working to achieve all
those requirements. We have replaced the
football pitch and laid it with new
grass, we have changed the seating, and
we are changing the floodlights to
achieve the required lux (illumination
level).”
Al Habtoor Engineering Enterprises is the main
contractor for the project, and is also
working with a number of specialised
subcontractors who are dealing with the
roof canopy, MEP services, the seating,
scoreboard and floodlights.
“This job was offered for special tender to a few
contractors who have a good reputation
and the ability to get the job done
quickly, as the time scale is an
important factor,” Mr. Abdullah said.
“A project of this type would normally
take 14-16 months to complete, but our
contract is nine months - so it is very
intensive.”
Work began on site at the beginning of April 2002, and
is expected to be completed by January
15 - in plenty of time for the start of
the championships in March.
“Between Al Habtoor Engineering Enterprises and the
subcontractors, we have about 750 people
working on the project,” said the
project manager. “The time limit is
the most crucial factor, but we are
confident the work will be completed in
time and to the standards and quality
for which we are renowned.”
For Yehia Abdullah, the stadium is his first project
for Al Habtoor Engineering Enterprises,
having joined the company in May.
Previously he worked as project manager
for a contracting company in
Abu
Dhabi
,
and also worked in
Kuwait
for a number of years after graduating
from the
University
of
Texas
in the
USA
in 1983.
“This is the first time I have worked on a stadium – but
construction is construction no matter
what you are building,” he said. “It
is an exciting project to be involved
with and I am looking forward to seeing
the new grandstand and other facilities
hosting such a major world event when
they are complete.”
As construction has been taking place, the nations
vying to compete in the championships
have been playing in qualifying
competitions around the world in a bid
to earn their place in the finals in the
UAE – and already 15 teams have
qualified following matches in
Asia
,
Europe
,
Central and
North
America
.
The
six teams refour countries representing
Central and North America will be the
United States, Canada, Mexico and
Panama.
The remaining nine countries will qualify over
the coming weeks from South America,
Africa (four from each continent) and
one from Oceania - with the
draw to decide which teams will play
against each other in the finals due to
take place in Abu Dhabi on January 29.
Mohsin Al Dossary, a member of the 2003 World Youth
Organising Committee, said the 24 teams
will be split into six groups of four
and will play in a league format before
the winners go through to the later
stages.
“Out of the six groups in the preliminary league,
two will be played in Abu Dhabi and
Dubai, while Al Ain and Sharjah will
stage one group each,” he explained.
|