Duhail Project handover ahead of schedule

by The Media Office

Duhail RPS.

HLG has handed over the reservoir and pumping station (RPS) milestone one (MS1) project in Duhail, Qatar, with the Qatar General Electricity and Water Corporation (KAHRAMAA) connecting the Duhail RPS to the water network.

The pumping station, one 21MIG reservoir and associated pipelines were commissioned into service nearly four weeks ahead of the scheduled date. HLG is constructing a total of six conc rete reservoirs, a pump house, associated buildings, road works, and landscaping for the Duhail Water Station project.

The scope of the work also includes the installation of a 15.9 kilometre water distribution pipeline and a control and instrumentation system.

The project is part of the QAR 751 million (DHS 772 million) development of new and independent water infrastructure facilities in the Duhail and Umm Qarn communities on the outskirts of Doha.